105 Residences at JVC, Dubai

Construction progress

105 Residences at JVC, Dubai construction updates

JVC · Kamdar Property Development L.L.C

Under constructionLast site inspection October 15, 2026 · 23 days ago
12.5%complete

When DLD first inspected the site on Oct 1, 2024, it was 0% complete. After 6 inspections it now stands at 12.5%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 12.5%
Construction started
March 1, 2025
Completion date registered with DLD
February 28, 2027
Site inspections
6
Units
105
Escrow bank
Mashreq Bank Psc
DLD project no.
3310

Latest site photos

October 15, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 15, 2026

    3 months after the previous inspection

    +2.3%12.5%
  2. July 13, 2026

    3 months after the previous inspection

    +6.5%10.1%
  3. April 2, 2026

    4 months after the previous inspection

    +2%3.6%
  4. December 11, 2025

    5 months after the previous inspection

    +1.3%1.6%
  5. July 11, 2025

    9 months after the previous inspection

    +0.3%0.3%
  6. October 1, 2024

    First inspection

    0%

Thinking about 105 Residences at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3310), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.