08 Life Residences at Dubai International City

Construction progress

08 Life Residences at Dubai International City construction updates

International City Dubai · Deniz Properties L.L.C

Under constructionLast site inspection August 26, 2026 · 2 months ago
64.9%complete

When DLD first inspected the site on Mar 25, 2025, it was 9.2% complete. After 5 inspections it now stands at 64.9%.

That is about 3.3% more of the building completed each month on average.

First inspection · 9.2%Latest · 64.9%
Construction started
October 5, 2024
Completion date registered with DLD
May 31, 2026
Site inspections
5
Units
107
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3590

Latest site photos

August 26, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. August 26, 2026

    4 months after the previous inspection

    +16.8%64.9%
  2. April 30, 2026

    4 months after the previous inspection

    +12.2%48%
  3. December 22, 2025

    3 months after the previous inspection

    +12.2%35.8%
  4. September 15, 2025

    6 months after the previous inspection

    +14.3%23.6%
  5. March 25, 2025

    First inspection

    9.2%

Thinking about 08 Life Residences at Dubai International City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3590), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.